Maintenance

Replacement of bicycle bridge wheels

During an inspection of a bicycle bridge, we noticed that the wheels had almost reached their wear limit. Not an urgent issue yet, but the ideal moment to intervene and prevent more serious damage.

To minimise the impact on production, the intervention was carefully planned:

  • Removal of the worn wheels
  • Installation of new wheels according to the correct tolerances
  • Inspection and alignment of the wheel track

The work was carried out on a Saturday, outside the customer’s operational hours, allowing everything to proceed smoothly and without disruption.

Result: a reliable installation once again, without impact on production and without the risk of unexpected downtime.